Mining · Nigeria

Obtain a mineral title / mining licence

Acquire a mineral title from the Mining Cadastre Office (reconnaissance permit, exploration licence, small-scale or full mining lease, quarry lease): choose title → apply at MCO → pay fees → grant (first-come, first-served on area).

4
steps
1
agency involved
Who you will deal with
Mining Cadastre Office (MCO)
The steps
  1. 1Choose the mineral title and confirm eligibility
    Agency
    Mining Cadastre Office (MCO)
    What is required
    Select the appropriate title (applicant must be a Nigerian citizen or a company incorporated in Nigeria). Types & fees: Reconnaissance Permit ₦300,000; Exploration Licence ₦600,000 (3 yrs, ≤200 km²); Small-Scale Mining Lease ₦300,000 (5 yrs, ≤3 km²); Mining Lease ₦3,000,000 (25 yrs, ≤50 km²); Quarry Lease ₦600,000; Water Use Permit ₦300,000.
    Documents
    CAC incorporation (for companies); proof of eligibility
    Typical timeline
    Selection stage
  2. 2Apply at the Mining Cadastre Office
    Agency
    Mining Cadastre Office (MCO)
    What is required
    Obtain and complete the application form and submit in triplicate with required documents. A Mining Lease additionally requires a pre-feasibility study and a minimum work programme signed by a COMEG-registered professional.
    Documents
    Completed form (x3); pre-feasibility study & COMEG-signed work programme (mining lease)
    Typical timeline
    Application stage
  3. 3Pay processing and service fees
    Agency
    Mining Cadastre Office (MCO)
    What is required
    Pay the title processing fee plus the annual service fee (₦31,500 per cadastral unit for the first time).
    Documents
    Evidence of fee payment
    Typical timeline
    On application
  4. 4Grant of the mineral title
    Agency
    Mining Cadastre Office (MCO)
    What is required
    The MCO checks area availability (first-come, first-served) and grants the title.
    Documents
    Complete application
    Typical timeline
    ≤30 working days (permits/licences); ≤45 (leases)

Primary source: https://www.miningcadastre.gov.ng/faq · confidence: high

The numbers behind the decision

Knowing the process is half of it. ONYX also tracks the operating environment you are entering — daily grid generation, official FX, state-level input prices and inflation, and sector output — each figure source-linked and dated.

ONYX publishes what the responsible agencies publish, with a link to each source. Requirements, fees and timelines change, and an officer's reading of a rule can differ from the published text. Verify against the linked source before you commit money — this is reference information, not legal advice.

ONYX Data & Intelligence · hello@onyxdata.io