Sector licencesMiningNigeria
Obtain a mineral title / mining licence
Acquire a mineral title from the Mining Cadastre Office (reconnaissance permit, exploration licence, small-scale or full mining lease, quarry lease): choose title → apply at MCO → pay fees → grant (first-come, first-served on area).
- Procedure
- 4steps
- Coordination
- 1agency
- Category
- Sector licencesMining
Task links
Go to the exact next page
Application, requirements, forms, fees, and tracking are labelled separately.
Routing map
Who you will deal with
Mining Cadastre Office (MCO)
Procedure
The steps, in order
Each route below is scoped to the step it can actually complete.
01 Choose the mineral title and confirm eligibility
- Agency
- Mining Cadastre Office (MCO)
- What is required
- Select the appropriate title (applicant must be a Nigerian citizen or a company incorporated in Nigeria). Types & fees: Reconnaissance Permit ₦300,000; Exploration Licence ₦600,000 (3 yrs, ≤200 km²); Small-Scale Mining Lease ₦300,000 (5 yrs, ≤3 km²); Mining Lease ₦3,000,000 (25 yrs, ≤50 km²); Quarry Lease ₦600,000; Water Use Permit ₦300,000.
- Documents
- CAC incorporation (for companies); proof of eligibility
- Typical timeline
- Selection stage
02 Apply at the Mining Cadastre Office
- Agency
- Mining Cadastre Office (MCO)
- What is required
- Obtain and complete the application form and submit in triplicate with required documents. A Mining Lease additionally requires a pre-feasibility study and a minimum work programme signed by a COMEG-registered professional.
- Documents
- Completed form (x3); pre-feasibility study & COMEG-signed work programme (mining lease)
- Typical timeline
- Application stage
03 Pay processing and service fees
- Agency
- Mining Cadastre Office (MCO)
- What is required
- Pay the title processing fee plus the annual service fee (₦31,500 per cadastral unit for the first time).
- Documents
- Evidence of fee payment
- Typical timeline
- On application
04 Grant of the mineral title
- Agency
- Mining Cadastre Office (MCO)
- What is required
- The MCO checks area availability (first-come, first-served) and grants the title.
- Documents
- Complete application
- Typical timeline
- ≤30 working days (permits/licences); ≤45 (leases)