Obtain a filling-station (retail outlet) licence
License a petrol filling station with NMDPRA under the PIA 2021: site suitability → Approval to Construct → build + witnessed tank test → storage & retail outlet licence.
- Procedure
- 4steps
- Coordination
- 2agencies
- Category
- Sector licencesEnergy
Task links
Go to the exact next page
Application, requirements, forms, fees, and tracking are labelled separately.
Routing map
Who you will deal with
NMDPRANMDPRA / NUPRC
Procedure
The steps, in order
Each route below is scoped to the step it can actually complete.
01 Apply for site suitability inspection
- Agency
- NMDPRA
- What is required
- Apply to NMDPRA for a site suitability inspection. Siting rules: pump ≥15 m from the road edge; ≥400 m between stations; ≤4 stations per 2 km stretch of road.
- Documents
- Site details; land documents; application (celps.nmdpra.gov.ng)
- Typical timeline
- Inspection stage
02 Obtain Approval to Construct (ATC)
- Agency
- NMDPRA
- What is required
- On a favourable suitability report, submit documents for review; NMDPRA issues the Approval to Construct.
- Documents
- Suitability report; engineering drawings; submitted documents
- Typical timeline
- After review
03 Construct and pass witnessed tank tests
- Agency
- NMDPRA / NUPRC
- What is required
- Build the station (minimum 3 underground tanks and 3 pumps for PMS, DPK, AGO). NUPRC witnesses tank burial and the pressure/leak test.
- Documents
- Constructed facility; tank test
- Typical timeline
- Construction period
04 Obtain the storage & retail outlet licence
- Agency
- NMDPRA
- What is required
- Apply for the licence to store and sell petroleum products and operate the station. Licence fee ₦2,000,000.
- Documents
- ATC; completed & tested facility; fee payment
- Typical timeline
- ~4-8 weeks from complete submission